South Beach carpark works

Works at South Beach are now complete and all carpark areas have reopened to the community.


South Beach carpark upgrade project

The South Beach carpark upgrade has now been completed as part of the City’s Infrastructure Improvement Program. The project has delivered increased parking and improved access for beach users.

The City thanks the community for their patience during construction.

Find out more about the changerooms project and carpark upgrades via the FAQs below.

The City will be upgrading and increasing car parking at South Beach as part of this year’s Infrastructure Improvement Program.

With a growing population and longer summers, beach usage has increased and put extra demand on the existing infrastructure.

While carpark extensions were not specified in the original place plan, they were to be reviewed and subsequently the City has listened to community feedback and decided to increase the capacity of the carparks.

This will hopefully reduce the reliance on and degradation of Wilson Park, a recreation reserve, which has been used as overflow parking during peak periods.

The works will create an additional 58 car bays (updated 31 July):

  • 12 in the northern car park
  • 44 + 2 ACROD in the southern car park

On 31 July the City revised the plans reconfiguring the parking on the eastern side, from 90-degree parking to parallel parking, to reduce the width and impact on nearby vegetation. There has also been the addition of a path from the dual use path in the northern car park, with suitable treatments to assist cyclists with slowing down as they enter the car park.

Download the plans for the carpark upgrade via the links below:

Central carpark

Northern carpark

Southern carpark

The City will still promote active transport as the preferred method of getting to the beach but acknowledges that walking or cycling is not possible for everyone.

Works are expected to be completed on 14 November 2025, weather permitting.

Footpath and vehicle access may be restricted in and around the South Beach area, and alternative access will be provided where possible. Parking within the construction area is strictly prohibited during the works and street parking adjacent to the site will also be temporarily closed.

Please keep an eye out for the message boards will in place to keep road users informed during closures.

Yes. The City will plant two new trees for every one removed as part of this project, in line with the City’s Trees on City Owned or Managed Land Council Policy.

Changeroom project update

The South Beach changerooms opened on Monday 28 July 2025!

The next phase of works will see the City upgrading the carparks at South Beach as part of this year’s Infrastructure Improvement Program.

 

The initial South Beach Facilities Schematic Design and associated landscape and access works were approved in principle at a Council meeting on 26 October 2022. It was also requested that the CEO to establish a Reference Group consisting of elected members, staff and targeted stakeholders including the South Beach swimmer group to progress with the detailed design and tender of the South Beach Facilities Project, with the CEO having delegated authority to approve the final design.

Carried: 12/1
For: Mayor Hannah Fitzhardinge, Cr Jenny Archibald, Cr Su Groome, Cr Ben Lawver, Cr Fedele Camarda, Cr Frank Mofflin, Cr Doug Thompson, Cr Bryn Jones, Cr Marija Vujcic, Cr Andrew Sullivan, Cr Rachel Pemberton, Cr Adin Lang
Against: Cr Geoff Graham

At its 20 December 2023 meeting Fremantle Council voted to reject the two tenders submitted to construct the new South Beach toilet and changerooms due to the submitted amounts being significantly above cost estimates and the approved budget.

The new changeroom facility was opened on 28 July 2025.

Share this page
Back to of the page